Yampa Integrated Water Management Plan Subcommittee Projects

YIWMP Subcommittee identified projects

Using the IWMP recommendations and the Yampa-White-Green Basin Roundtable Basin Implementation Plan Identified Priority Projects (IPP) the YIWMP subcommittee has grouped the projects into three categories:

  • Tracking – Tring to find a way to assist an on-going project
  • Monitoring – project is funded and running, the committee will only follow it to verify it gets accomplished
  • Not tracked – projects either has no proponent, is on hold, will be worked on in the future time, or is being run by an organization that is capable of funding the project and completing it

Using this grouping the subcommittee will only work on the tracking projects and monitor the projects that need monitoring.  The not tracked projects will be reviewed as time allows or as when needed.

YIWMP Subcommittee projects: Tracking

The below table is the projects the YIWMP subcommittee is tracking to find a way to assist an on-going project

Projected ID
2022-IWMP-01
2022-IWMP-02
2022-IWMP-03
2022-IWMP-04
2022-IWMP-05
2022-IWMP-06
2022-IWMP-08
2022-IWMP-09
2022-IWMP-10
2022-IWMP-11
2022-IWMP-12
2022-IWMP-13
2022-IWMP-15
2022-IWMP-17
2022-IWMP-18
2022-IWMP-20
YW-2015-0027
YW-2015-0028
YW-2015-0030
YW-2020-0011
YW-2020-0016
YW-2020-0036
YW-2020-0045
YW-2020-0049
YW-2020-0054
YW-2023-0001
YW-2023-0004
Lead Agency/Contact Person
Michele Meyer/Lindsey Marlow
Michele Meyer
Michele Meyer
Claire Sollars
Jennifer Wellman
Andy Rossi
Lindsey Marlow/Kent Vertrees
Lindsey Marlow/Kent Vertrees
Tim Sullivan/Ryan Messinger
Andy Rossi
Michele Meyer
Gena Hinkemeyer
Brian Hodge/Ian Wilson/Andy Rossi
Julie Baxter
Lyn Halliday
Lindsey Marlow/Kent Vertrees
Jennifer Wellman
David Graf
Jennifer Wellman
Lindsey Marlow/Kent Vertrees
Julie Baxter/Lindsey Marlow
Jennifer Wellman
Tom Holliday/David Torgler
No Proponent - UYWCD?
Lindsey Marlow/Kent Vertrees
UYWCD,YVSC,Scrips,
Lindsey Marlow/FOY
Project Comments
A portion of this project is a part of YRSP (IWMP-9), LT funding Needed
Currently no strategy in how to move this project forward
Project has yet to formally begin due to current capacity
Project is two fold, ditch governance & education on new rules
Project is in planning stages,look at highlighting multi-benefit projects
Project in planning stages, still identifying reqd. improvement
Project on-going, LT funding reqd. Landowners cooperation
This project has been incorporated into YW-2023-0004 YR Stewardship Program
This project has been incorporated into YW-2023-0004 YR Stewardship Program
Four of six reservoirs need assistance, one may be abandoned
Pilot programming is running for at least 3 to 6 more months
On-hold. Funding is a problem for staff to assist.
Draft plan is complete, needs to go out to review and modeling advice
Needs a partner to implement, and LT funding
Project on-going filling in data gaps. NRCS funding may be available?
Contractor developing a plan to identify imperiled in-stram flows
Beginning of YW-2020-35 & YW-2020-36
Having discussions with various stake-holders, no definitive action yet
Project in planning stages, need funds to study problem
Project deliverables are a part of Yampa River Stewardship Project
Engineering/Environmental Survies funded, project complete by 2029
Community meetings in 2024, construction after that
Interim repairs funded by BRT underway, repair study on-going
This project is following the WRIWI Return Flow Study currently underway
Plans to run until 2030 at least if funded
Phase II is 8 additional moisture monitors station being installed
Next phase of project is to receive funding for project estimated at $150K/Yr. This project incorporates IWMP Recommendations #9 and #10

YIWMP Subcommittee projects: Monitor

The below table is the projects the YIWMP subcommittee is monitoring

Projected ID
2022-IWMP-07
2022-IWMP-16
2022-IWMP-19
2022-IWMP-0017
2022-IWMP-0019
2022-IWMP-0023
2022-IWMP-0031
2022-IWMP-0034
2022-IWMP-0037
2022-IWMP-0003
2022-IWMP-0010
2022-IWMP-0012
2022-IWMP-0013
2022-IWMP-0015
2022-IWMP-0035
2022-IWMP-0050
YW-2015-0002
YW-2015-0003
Lead Agency/Contact Person
Emily Lowell
Emily Lowell
David Graf
Geovany Romero
Frank Alfone
Peter Vrixius/Melaniw Kilpatrick
Julie Baxter
Ben Beall/BLM
Lindsey Marlow/Kent Vertrees
Frank Alfone
Geovany Romero
Jennifer Wellman
Andy Rossi
Brian Hodge/Ian Wilson
Jennifer Wellman
No Proponebt; Ask Andi Rossi
YVSC
Routt and Moffat Counties
Project Comments
Initial Funding received, project on-going, do not need immed. Help
On-hold currently. Partner capacity is the biggest issue
Having discussions when needed
Three subdivision requests are before Routt County P&Z
Complete by end of 2023
Awaiting last ACOE permit, the project should complete by 2025
Continuing to develop longer term plan, monitoring short-tern results
Project funded through NWFW grant, complete by Nov 2027
When Bear River Park opens this will be more of a priority
Project on-going. Continual planning will be required.
begin work in September and complete by year end 2023
Project begins in fall 2023, complete in 2024, or early 2025
Stalled by FS authorization and permitting requirements
Phase I complete 2022, Phase 2 funded, will finish fall of 2024
Complete in late Fall 2023
Work on this is being done by the Yampa Dashboard Group
NEPA should be done by year-end. Field work will begin in Spring
Continuing to work with biological controls and educating public

YIWMP Subcommittee projects: NOT Tracked

The below table is the projects the YIWMP subcommittee is not tracking

Projected ID
2022-IWMP-14
YW-2015-0001
YW-2015-0002
YW-2015-0008
YW-2015-0010
YW-2015-0013
YW-2015-0014
YW-2015-0018
YW-2015-0021
YW-2015-0024
YW-2015-0024
YW-2015-0029
YW-2015-0033
YW-2015-0033
YW-2015-0035
YW-2015-0038
YW-2020-0001
YW-2020-0002
YW-2020-0004
YW-2020-0014
YW-2020-0017
YW-2020-0018
YW-2020-0019
YW-2020-0044
YW-2020-0046
YW-2020-0047
YW-2020-0048
YW-2020-0051
YW-2020-0052
YW-2020-0053
YW-2020-0056A
Lead Agency/Contact Person
Andy Rossi
Hunter Causey/Rebecca Briesmoore
Frank Alfone
Andy Rossi
Matt Brown
Andy Rossi
Frank Alfone
Julie Baxter
Hunter Causey/Jennifer Wellman
Rick Henderson
Rick Henderson
David Graf
Ben Krause, CPW
Ben Krause, CPW
Drew Johnroe
Did not send out yet. To whom?
Julie Baxter
Julie Baxter
Andy Rossi
Mike Robinson
Tamara Neuman
David Graf
Ken Brenner
Ken Brenner
No Proponent
No Proponent
No Proponent
Andy Rossi
YWG BRT, UYWCD
Andy Rossi
Hunter Causey/Rebecca Briesmoore
Project Comments
IWMP Reservoir Coordination Group and others are already do this
No plans to move this project forward at this time
Time frame for this project is 2030 to 2040
On-hold. Another alternative is being considered
20 year planning horizon, planning for permits & studies on-going.
Best of the three alternatives, investigation going forward
Project runs through 2027
2030 and beyond is time horizon for water plant. Planning is on-going
No date set for this project
Awaiting Rick Henderson to return update
Awaiting Rick Henderson to return update
In plans for next 5 to 10 years
Awaiting Ben Krause to return update
Awaiting Ben Krause to return update
project completed fall 2022, monitoring continues through 2027
No proponent
City of SBS may work on in the future
Plan complete, following plan recommendations
On-hold. Another alternative is being considered
Project funded and running
LSP study final, project complete?
Exploring how net might be attached to outlet structure
Project funded, on-track to complete this year, or early next year
Project funded until 2025, on-going commitment of YWG BRT
No proponent
No proponent
No proponent, CSU Study?
No plan for when this would kick off
No proponent
2020 Repairs are complete, lining of ditch still pending
Yampa River Flow Pilot Project implemented in 2021